Attached is the schedule of our pre-arranged power interruptions for May 23
to 29, 2011. This serves as a general information guide and should not be
directly construed as an interruption advisory to the e-mail recipients.

Please call us at telephone numbers 16211 or 631-1111 for verification of
power interruption schedule.

If you wish to unsubscribe, please send us an e-mail and type in the word
"Unsubscribe".

Thank you very much.




MAINTENANCE SCHEDULE

To carry out necessary maintenance and upgrading works on various
MERALCO distribution facilities, electric service will be temporarily
interrupted on the following dates and places:


TUESDAY, MAY 24, 2011
LAGUNA (STA. CRUZ, PILA, LILIW AND NAGCARLAN)
BETWEEN 10:00AM AND 11:00AM AND THEN BETWEEN 5:00PM AND 6:00PM – THE
WHOLE OF CIRCUITS STA. CRUZ 322WF, 32WF, 34WF AND 35WF
The whole of Sta. Cruz.
The whole of Pila excluding Carmen Agra Subd. and Purok Codera
in Bgys. San Antonio and Bulilan Sur.
Bgys. Daniw and Dita in Liliw.
Portion of Bgys. Banca-banca, Manaol, Maravilla, Sibulan and
Wakat in Nagcarlan.

REASON: Repair of badly leaning poles along 69kV Caliraya – Sta.
Cruz transmission lines.

TUESDAY TO WEDNESDAY, MAY 24 – 25, 2011
QUEZON CITY
BETWEEN 11:00PM (TUE., 05/24/11) AND 4:00AM (WED., 05/25/11) –
PORTION OF CIRCUIT CUBAO 43VQ
Portion of Gen. Romulo Ave. from P. Tuazon St. to McArthur Ave.
including RCBC Bank, Fernandina 88 Suites and Ali Mall 1 & 2 in
Araneta Center, Bgy. Socorro, Cubao.

REASON: Reconstruction works along Gen. Romulo Ave. in Araneta
Center, Cubao, Quezon City.

WEDNESDAY TO SATURDAY, MAY 25 TO 28, 2011 (DAILY)
LAGUNA (STA. CRUZ, PILA, LILIW AND NAGCARLAN)
BETWEEN 7:00AM AND 8:00AM AND THEN BETWEEN 5:00PM AND 6:00PM – THE
WHOLE OF CIRCUITS STA. CRUZ 322WF, 32WF, 34WF AND 35WF
The whole of Sta. Cruz.
The whole of Pila excluding Carmen Agra Subd. and Purok Codera
in Bgys. San Antonio and Bulilan Sur.
Bgys. Daniw and Dita in Liliw.
Portion of Bgys. Banca-banca, Manaol, Maravilla, Sibulan and
Wakat in Nagcarlan.

REASON: Repair of badly leaning poles along 69kV Caliraya – Sta.
Cruz transmission lines.

WEDNESDAY, MAY 25, 2011
BATANGAS CITY
BETWEEN 9:00AM AND 9:30AM – PORTION OF CIRCUIT BOLBOC 33ZV – BATANGAS
326SG
Portion of P. Herrera St. from C. Tirona St. to Sitio Hilltop
including Ferry Road; Dolar Subd., Villanueva Subd.; Teachers
Conference Center and Lyceum of Batangas in Bgys. Kumintang Ibaba and
Batangas City proper.
Portion of P. Burgos St. from Meralco - Bolboc substation to
Manila - Batangas Highway including Kabatay Subd. in Bgy. Calicanto.

BETWEEN 11:00AM AND 2:00PM – PORTION OF CIRCUIT BATANGAS 324SG
Portion of Batangas City Diversion Road from near Meralco -
Batangas City substation to and including Buenafe Country Villas,
Batangas City Village and Wilcon Builders in Bgys. Alangilan and
Balagtas.

BETWEEN 12:30PM AND 2:00PM – PORTION OF CIRCUIT BATANGAS 324SG
Portion of Gov. Carpio St. from P. Herrera St. to and including
Sitio Silangan; and Mckinley High School in Bgys. Kumintang Ibaba,
Kumintang Ilaya and Gulod Labac.

REASON: Commissioning of new feeder circuit 13.8kV Batangas
323SG.

FRIDAY TO SATURDAY, MAY 27 – 28, 2011
QUEZON CITY
BETWEEN 11:00PM (FRI., 05/27/11) AND 5:00AM (SAT., 05/28/11) –
PORTION OF CIRCUIT KAMUNING 43VP
Portion of Epifanio Delos Santos Ave. (EDSA) from Manila
Seedling Bank to and including Eton Centris Walk, Eton Centris IT
Bldg., Eton Station, Eton SM Hypermarket, Bantayog ng mga Bayani in
Bgys. Central and South Triangle.

REASON: Relocation of facilities along Epifanio Delos Santos Ave.
(EDSA) near Quezon Ave. in Bgy. Central, Quezon City.

SATURDAY, MAY 28, 2011
BULACAN (HAGONOY AND PAOMBONG)
BETWEEN 3:00PM AND 4:00PM – PORTION OF CIRCUITS CALUMPIT 32YQ; AND
MALOLOS 324YV
Portion of San Agustin Road from Contreras Ville to Paombong –
Hagonoy Provincial Road including Bgy. San Agustin in Hagonoy.
Portion of Paombong – Hagonoy Provincial Road and San Agustin
Road from Pandohan Road to and including Bgys. San Agustin, San Pedro
and Sto. Rosario in Hagonoy.
Bgy. San Isidro in Paombong.

REASON: Maintenance works inside Meralco - Calumpit substation.

SUNDAY, MAY 29, 2011
LAGUNA (STA. CRUZ, PILA, LILIW AND NAGCARLAN)
BETWEEN 7:00AM AND 8:00AM AND THEN BETWEEN 6:00PM AND 7:00PM – THE
WHOLE OF CIRCUITS STA. CRUZ 322WF, 32WF, 34WF AND 35WF
The whole of Sta. Cruz.
The whole of Pila excluding Carmen Agra Subd. and Purok Codera
in Bgys. San Antonio and Bulilan Sur.
Bgys. Daniw and Dita in Liliw.
Portion of Bgys. Banca-banca, Manaol, Maravilla, Sibulan and
Wakat in Nagcarlan.

REASON: Repair of badly leaning poles along 69kV Caliraya – Sta.
Cruz transmission lines.

MANDALUYONG CITY
BETWEEN 9:00AM AND 2:00PM – PORTION OF CIRCUIT NEW ROCKWELL 412VV –
PANDACAN 43M
Portion of Acacia Lane from Shaw Blvd. to and including
Pinagtipunan St. in Bgy. Hagdang Bato Libis.

REASON: Replacement of rotten pole along Acacia Lane in Bgy. Hagdang
Bato Libis, Mandaluyong City.




MERALCO exerts all efforts to restore electric service as scheduled.
However, there are instances when due to unavoidable circumstances,
restoration may extend beyond the published schedule.
For more information, please contact our CALL CENTER at telephone
nos. 16211 / 631-1111, fax nos. 1622-8554 / 1622-8556, or e-mail address
callcenter.tech.assist@meralco.com.ph. For faster resolution of inquiries,
please use the Bill ID Number or Service Identification Number (SIN)
indicated in your electric bills.
For those who prefer to receive this schedule via e-mail, simply
write to us at callcenter.tech.assist@meralco.com.ph and type in the phrase
"Request for weekly schedule".




VIEW YOUR BILL ON LINE. VISIT OUR WEBSITE!
www.meralco.com.ph



Privileged/Confidential information contained in this e-mail and its attachment/s is intended solely for the use of the addressee and is not meant for reproduction, disclosure and distribution to others without previous authorization from Meralco or its authorized representative. If erroneously sent or received, please do not open and delete the same from your system. Unless, otherwise specifically stated and confirmed by the authorized representative of Meralco, the opinions and views that may be contained therein are personal to the sender.