Monday, February 15, 2016

MERALCO Maintenance Schedule for February 15 - 21, 2016 (Grp2) (Sent by: Janice De Asis)

=======================================================================
WELCOME TO MERALCO'S MAINTENANCE SCHEDULE VIA E-MAIL
------------------------------------------------------------------------------------------------------------------

Attached is the schedule of our pre-arranged power interruptions (ppi) for February 15 to 21, 2016.  This serves as a general information guide and should not be directly construed as an interruption advisory to the e-mail recipients.

Please call us at telephone numbers 16211 or 631-1111 for verification of power interruption schedule.

If you wish to unsubscribe, please send us an e-mail and type in the word "Unsubscribe".

Thank you very much.



MAINTENANCE SCHEDULE

To carry out necessary maintenance and upgrading works on various MERALCO distribution facilities, electric service will be temporarily interrupted on the following dates and places:


SUNDAY TO MONDAY, FEBRUARY 14 - 15, 2016
QUEZON CITY (GREATER FAIRVIEW)
    BETWEEN 11:00PM AND 11:30PM (SUN., 02/14/16) AND THEN BETWEEN 4:30AM AND 5:00AM (MON., 02/15/16) – PORTION OF CIRCUIT NOVALICHES 49YJ
    Portion of Regalado Highway from near Bronx St. to Quirino Highway including Braceville, Bradley, Bremley, Bristol and Brookside Sts. in Fairmont Subd.; Ipil and Narra Sts. in Neopolitan Subd. Ph 6; Neopolitan I Villa Vienna; Blocks 139 & 163 in Neopolitan V Casamilan in Bgys. Greater Lagro, North Fairview and Pasog Putik.
    Portion of Mindanao Ave. from near New Haven Village to Neopolitan I Villa Vienna including Neopolitan Business Park, Neopolitan Estate and Neopolitan IV Britanny Subd. in Bgys. Greater Lagro and Pasog Putik.

    BETWEEN 11:00PM (SUN., 02/14/16) AND 5:00AM (MON., 02/15/16) – PORTION OF CIRCUIT NOVALICHES 49YJ
    Portion of Regalado Highway from near Acacia St. to and including Bronx, Adrian, Badger, Baker, Banning, Bergen, Bremen, Bronson, Bryant, Burney and Butler Sts. in Fairmont Subd.; and Bascom St. in North Fairview Subd. in Bgys. North Fairview and Pasong Putik.

    REASON:     Various line maintenance works along Regalado Highway in North Fairview, Bgy.  Pasong Putik, Greater Fairview, Quezon City.

MONDAY TO TUESDAY, FEBRUARY 15 - 16, 2016
PARAÑAQUE CITY
    BETWEEN 11:00PM AND 11:30PM (MON., 02/15/16) AND THEN BETWEEN 3:30AM AND 4:00AM (TUE., 02/16/16) – PORTION OF CIRCUIT BF - PARAÑAQUE 422WU
    Portion of Multinational Ave. from Mathew St. to and including Ambasador Hills, Andrew, John, John Paul, Jude, Philip, Rogationist, Simon, Thomas and Timothy Sts. in Multinational Village, Bgy. Moonwalk; Dollar Lane, Franc Lane Rupee Lane and Escudo Lane Sts. in Villanueva Village, Bgy. San Dionisio.

    BETWEEN 11:00PM (MON., 02/15/16) AND 4:00AM (TUE., 02/16/16) – PORTION OF CIRCUIT BF - PARAÑAQUE 422WU
    Portion of Dollar Lane St. from Schilling Lane St. to near Lire Lane St. in Villanueva Village, Bgy. San Dionisio.

    REASON:     Replacement of rotten pole and other line works along Schilling Lane St. in Villanueva Village, Bgy. San Dionisio, Parañaque City.

MANDALUYONG CITY
    BETWEEN 11:00PM (MON., 02/15/16) AND 4:00AM (TUE., 02/16/16) – PORTION OF CIRCUIT PANDACAN 12M
    Portion of A. Mabini St. from Rev. Aglipay St. to and including Villarica, Pananalig and Nanirahan Sts. in Bgy. Mabini – J. Rizal.

    REASON:     Installation of new facilities along A. Mabini St. in Bgy. Mabini – J. Rizal, Mandaluyong City.

TUESDAY, FEBRUARY 16, 2016
CAVITE (INDANG)
    BETWEEN 10:00AM AND 2:00PM – PORTION OF CIRCUIT TAGAYTAY WEST 314TGW
    Portion of Bgy. Guyam – Harasan Road from Indang – Alfonso Road to and including Bgys. Pulo, Harasan and Guyam Malaki.

    REASON:     Relocation of primary facilities along Bgy. Guyam - Harasan Road in Bgy. Harasan, Indang, Cavite.
BULACAN (SAN MIGUEL)
    BETWEEN 10:00AM AND 2:00PM – PORTION OF CIRCUIT SAN MIGUEL 34YN
    Portion of Cagayan Valley Road from Meralco – San Miguel substation to and including D. Labrador, San Vicente, Old Sta. Rita and Viola Sts. in Bgys. San Agustin, San Vicente and Sta. Rita Matanda.

    REASON:     Relocation of primary facilities affected by DPWH repair works at Oriente Bridge along Cagayan Valley Road in Bgy. San Vicente, San Miguel, Bulacan.
LAGUNA (PILA)
    BETWEEN 10:00AM AND 3:00PM – PORTION OF CIRCUIT STA. CRUZ 32WF
    Portion of Labuin – Bagong Pook Barangay Road from Pila – Sta. Cruz Municipal Road to and including Pook Bayside, Purok IV and Pook Hingiwan; Villa Concepcion and Tierra Verde Subd. in Bgys. Bagong Pook and Labuin.

    REASON:     Line conversion works along Labuin – Bagong Pook Barangay Road in Bgys. Labuin and Bagong Pook, Pila, Laguna.
*QUEZON CITY (NOVALICHES)
    BETWEEN 8:00AM AND 4:00PM – PORTION OF CIRCUIT NOVALICHES 43YJ
    Portion of Nenita Ext. including Tarhaville Subd. in Bgys. Gulod and Sta. Lucia.

    REASON: Line reconductoring works along Nenita Ext. in Bgy. Gulod, Novaliches, Quezon City.

WEDNESDAY, FEBRUARY 17, 2016
MANILA (PACO, PANDACAN AND STA. ANA)
    BETWEEN 12:01AM AND 12:30AM AND 4:30AM AND 5:00AM – PORTIONS OF CIRCUITS PACO 423VY; AND STA. ANA 17VN
    Portion of Quirino Ave. from Meralco – Paco substation to and including Philippine Columbian Association Sports Club and PNR Warehouse in Paco.
    Portion of Pedro Gil St. from Quirino Ave. to Meralco – Sta. Ana substation near Dr. M. L. Concepcion St. including Fabmar Compound in Paco and Sta. Ana.
    Portion of Peñafrancia St. from Sto. Sepulcro St. to near Sto. Antonio St. including Barangay 682 Zone 74 Barangay Hall in Paco.

    BETWEEN 12:01AM AND 5:00AM – PORTION OF CIRCUITS PACO 423VY; AND STA. ANA 17VN
    Portion of Pedro Gil St. from Felix St. to near Tejeron St. in Sta. Ana.
    Portion of Felix St. from Pedro Gil St. to and including Kahilom I, Kahilom II, Masigasig and Delas Alas Sts. in Pandacan and Sta. Ana.

    REASON:     Line reconductoring works and replacement of facilities along Pedro Gil St. in Sta. Ana, Manila.

LAGUNA (CABUYAO)
    BETWEEN 9:00AM AND 2:00PM – PORTION OF CIRCUIT LISP 413ZQ
    Portion of River Drive from near Pulo – Diezmo Road to and including East Road; Webforge Phils., Automated Technology and JY and Sons Realty in Light Industrial & Science Park 1, Bgy. Diezmo.

    REASON:     Installation of lightning protection devices; replacement of facilities; and line repair works along River Drive in Light Industry & Science Park 1, Bgy. Diezmo, Cabuyao, Laguna.
BATANGAS PROVINCE (BATANGAS CITY)
    BETWEEN 10:00AM AND 3:00PM – PORTION OF CIRCUIT BATANGAS 316SG
    Portion of Tinga Itaas Barangay Road from Tinga Labak Barangay Road to and including Tinga – Ibaan Road; and Barangay Tinga Day Care Center in Bgys. Tinga Itaas, Tinga Labak and Kumintang Ilaya.
    Portion of Tinga Itaas and Soro - Soro Barangay Roads from Southern Tagalog Arterial Road (STAR) to and including Mercedes Homes Subd.; Soro – Soro Ibaba Development Cooperative and Sovereign Shepherd School of Values and Learning in Bgys. Soro – Soro Ibaba, Soro – Soro Ilaya and Tinga Itaas.

    REASON:     Installation and retirement of facilities affected by DPWH road widening project along Tinga – Ibaan Road in Bgy. Tingga Itaas, Batangas City, Batangas Province.
LAS PIÑAS CITY; AND PARAÑAQUE CITY
    BETWEEN 10:00AM AND 3:00PM – PORTION OF CIRCUIT BF-PARAÑAQUE 44WU
    Portion of Angelina Canaynay Ave. from Dr. A. Santos Ave. in Bgy. San Dionisio, Parañaque City to Martinville Subd. including Doña Matilde Subd., Gatchalian Subd., Green Valley Compound and Olivarez & Guevarra Compound; and Immaculate Concepcion Parish in Bgy. Pulanglupa II, Las Piñas City; Don Jose Green Court Subd., Espiritu Compound, Gardenvale Subd.; Palanyag and South Sts.; Rogationist Fathers Seminary, S.S.I. Rubber Research Corp. and Poly Yuan Trading Corp. in Bgy. San Dionisio, Parañaque City.  

    REASON:     Installation of facilities along Angelina Canaynay Ave. in Bgy. San Dionisio, Parañaque City.

WEDNESDAY TO THURSDAY, FEBRUARY 17 – 18, 2016
CAVITE (KAWIT; AND NOVELETA)
    BETWEEN 11:00PM (WED., 02/17/16) AND 4:00AM (THU., 02/18/16) – PORTION OF CIRCUIT ROSARIO 43RS
    Portion of M. Salud Road from Camella – Noveleta Homes Subd. to Imus – Kawit Municipal boundary including Bgys. San Antonio I and II in Noveleta; and Bgy. San Sebastian in Kawit.

    REASON:     Relocation of primary facilities affected by DPWH road widening project along M. Salud Road in Bgy. Sta. Rosa II, Noveleta, Cavite.

BULACAN (MEYCAUAYAN CITY)
    BETWEEN 11:00PM AND 11:30PM (WED., 02/17/16) AND THEN BETWEEN 4:30AM AND 5:00AM (THU., 02/18/16) – PORTION OF CIRCUIT MEYCAUAYAN 43YM
    Portion of Gen. Pacheco St. and Hulo – Banga Road from near Saluysoy Road to near Meycauayan Doctor's Hospital including Northville 3 Subd.; Bayugo Road, Soriano, A. Ponciano, Bañez, C. Pascual, Isla Verde, Paraiso, M. Buñing, Marcos Ira, D. Digueño, Col. S. Castro, Parrian, F. Nito and Legaspi Sts.; Meycauayan West Central School, Meycauayan Market, Mercury Drug and Meycauayan Flood Gate in Bgys. Banga, Bayugo, Calvario, Hulo, Longos, Poblacion, St. Francis and Zamora.
    Portion of Bancal Road from Estraño St. to near MacArthur Highway including Col. M. Exaltacion, Ilang – Ilang, Jasmin and San Diego Sts.; Bancal Elementary School, Velenzuela Tannery Corp., Chem-Plast Manufacturing and Eastern Tanning Corp. in Bgy. Bancal.    

    BETWEEN 11:00PM (WED., 02/17/16) AND 5:00AM (THU., 02/18/16) – PORTION OF CIRCUIT MEYCAUAYAN 43YM        
    Portion of Malhacan Road from near North Luzon Expressway (NLEX) to MacArthur Highway including Doña Consolacion Village, Larusvil Subd., Sanville Homes Subd., Villa Dulalia Executive Village, Zigzag Hills Subd., Emily Ville Subd., SNC Compound, Sitio Bisita; Bagong Buhay, Bagong Silang, Bulak, Calle Fabrica and Pag-asa Sts.; 7-11 Store, St. Joseph House of Serenity, Chowking and Soroptomist International of Meycauyan in Bgy. Malhacan.
    Portion of Gen. Pacheco St. from MacArthur Highway to Saluysoy Road including Abacan, F. Dazo and Sampaguita Sts. in Bgys. Calvario and Saluysoy.

    REASON:     Installation of additional lightning protection devices along Malhacan Road in Bgy. Malhacan, Meycauayan City, Bulacan.

MANILA (TONDO)
    BETWEEN 11:30PM AND 11:59PM (WED., 02/17/16) AND THEN BETWEEEN 5:00AM AND 5:30AM (THU., 02/18/16) – PORTIONS OF CIRCUITS TUTUBAN 42VT AND 431VT
    Portion of Moriones St. from Meralco – Tutuban substation along Dagupan St. to Marcos Highway (Radial Road 10) including Barcelona, Madrid, Necodemus, C. P. Garcia, J. Nolasco, Tagumpay, Kagitingan, Mabuhay, Masinop, Morga, Nicolas Zamora, Ricafort, Salvacion, Sandico, Sevilla, Soliman, Sta. Maria, St. Mary, Tuazon, Wagas, Camba, Concha, Coral, F. Varona, Juan Luna, Nijaga, Pavia, Perla A & C, Pilapil, R. A. Reyes and Velazquez Sts.; Mary Johnston Hospital, Tondo High School and Isabelo Delos Reyes Elementary School.  
    Portion of Pacheco St. from Marcos Highway to and including Lacson, Melalcalde, Mata, San Sebastian,  Osmeña, Quirino, Quezon, Magsaysay, Laurel, C. P. Garcia, Sta. Fe, Malacapas, Dandan, Liwayway, Panday Pira, Myna, Canary, Aguho, Apitong, Romualdez, Katanas, Kamachile, Kalamansi, Kamias, Mansanita, Dalanghita and Atis Sts.

    BETWEEN 11:30PM (WED., 02/17/16) AND 5:30AM (THU., 02/18/16) – PORTION OF CIRCUITS TUTUBAN 42VT AND 431VT
    Portion of Marcos Highway (Radial Road 10) from Pacheco St. to near Zaragoza St. including Lorenzo Shipping.

    REASON:     Relocation of primary facilities along Marcos Highway (Radial Road 10) in Tondo, Manila.

PASAY CITY
    BETWEEN 11:30PM (WED., 02/17/16) AND 5:30AM (THU., 02/18/16) – PORTION OF CIRCUIT CBP1A 424RF
    Oceanaire Condominium Towers along Coral Way Drive in Central Business Park.

    REASON:     Replacement of facilities along Coral Way Drive in Central Business Park, Pasay City.

THURSDAY, FEBRUARY 18, 2016
QUEZON CITY (OLD BALARA)
    BETWEEN 9:00AM AND 2:00PM – PORTION OF CIRCUIT DILIMAN 45VU
    Portion of Katipunan Ext. from Buenavista Ville Subd. to and including Richville Subd. in Bgy. Old Balara.

    REASON:     Relocation of primary facilities along Vista Real Ave. in Vista Real Executive Subd., Bgy. Old Balara, Quezon City.

FRIDAY, FEBRUARY 19, 2016
LAGUNA (NAGCARLAN)
    BETWEEN 10:00AM AND 3:00PM – PORTION OF CIRCUIT BOTOCAN 41D
    Portion of Nagcarlan – Liliw Road from C. Lirio St. to and including Bgys. Sulsuguin, Alumbrado, Maiit, Palayan, Sabang, Talahib and Yukos.

    REASON:     San Pablo – Nagcarlan - Liliw Road widening in Bgy. Palayan, Nagcarlan Laguna.

SATURDAY, FEBRUARY 20, 2016
CALOOCAN CITY
    BETWEEN 9:00AM AND 1:00PM – PORTION OF CIRCUIT CAMARIN 432TC
    Portion of Camia St. in Malaria Subd., Bgy. Tala.

    REASON:     Line reconstruction works along Camia St. in Malaria Subd., Bgy. Tala, Caloocan City.

BULACAN (MEYCAUAYAN); AND VALENZUELA CITY
    BETWEEN 9:00AM AND 9:30AM AND THEN BETWEEN 2:30PM AND 3:00PM – PORTIONS OF CIRCUIT SAOG 415SAO
    Portion of MacArtur Highway from Aca Road to and including Buildersville Subd., San Simon Subd., Sumilang Subd. and Villa Encarnacion Subd.; and Fernando St. in Bgys. Dalandanan, Malanday, Malinta and Rincon in Valenzuela City.
    Portion of Aca Road from Bancal Ext. to and including First Valenzuela Industrial Compound in Bgy. Bancal, Meycauayan, Bulacan; and C. Molina St. in Bgy. Veinte Reales, Valenzuela City.

    REASON:     Retirement of facilities along MacArthur Highway in front of Iglesia Ni Cristo Church in Bgy. Dalandanan, Valenzuela City.

SUNDAY, FEBRUARY 21, 2016
BULACAN (CALUMPIT; HAGONOY; AND PLARIDEL)
    BETWEEN 4:00AM AND 4:30AM AND THEN BETWEEN 5:00PM AND 5:30PM – THE WHOLE OF CIRCUIT MALOLOS 34YV; AND PORTION OF CIRCUIT MALOLOS 325YV
    Portion of A. Mabini and Gov. F. Padilla Sts. from Meralco – Malolos substation to F. Vergel De Dios St. including Bgys. Pinagbakahan, Barihan and Santisima Trinidad in Malolos; Bgys. Agnaya, Banga 1st, Dampol, Lumang Bayan, Rueda, Sipat, Poblacion, Sta. Ines and Sto. Niño in Plaridel.
    Portion of Old Tabang Road and Cagayan Valley Road from F. Vergel De Dios St. to and including Bgys. Tabang and Sta. Ines in Plaridel; Bgys. Bungahan and Ligas in Malolos; and Bgy. Sta. Rita in Guiguinto.

    BETWEEN 8:00AM AND 11:00AM – PORTION OF CIRCUIT CALUMPIT 325YQ
    Portion of Calumpit - Hagonoy Municipal Road from Purok 6 in Bgy. Sta. Lucia, Calumpit to and including Bgys. Mercado, San Agustin, San Isidro, San Jose, San Juan, Sta. Monica, Sto. Niño and Tampok in Hagonoy; Bgys. Meyto, Panducot, San Jose and Sta. Lucia in Calumpit.

    BETWEEN 8:00AM AND 5:00PM – PORTION OF CIRCUIT CALUMPIT 325YQ
    Portion of MacArthur Highway from Meralco – Calumpit substation to and including Jed's Island Resort, Calumpit Water District New Bldg., St. John The Baptist Catholic School, Calumpit Institute and Holcim Phils.; Bgys. Balungao, Caniogan, Frances, Gatbuca, Iba O'Este, Palimbang, Poblacion, Sapang Bayan and Sucol in Calumpit; and Purok 2 in Bgy. Iba-Ibayo, Hagonoy.
    Portion of Calumpit - Hagonoy Municipal Road from MacArthur Highway to near Purok 6 in Bgy. Sta. Lucia including Bgys. Bulusan, Calizon, Gugo, Meysulao, and San Miguel in Calumpit.

    BETWEEN 11:00AM AND 5:00PM – PORTION OF CIRCUIT CALUMPIT 32YQ
    Portion of San Agustin – San Nicolas Barangay Road from near Purok 3 in Bgy. San Agustin to and including Bgys. Sagrada Familia, San Agustin, San Nicolas, San Pascual, San Roque, San Sebastian, Sta. Cruz, Sta. Elena, Sto. Niño and Sto. Rosario in Hagonoy.
REASON:     Various line maintenance works inside Meralco – Calumpit substation.
    MERALCO exerts all efforts to restore electric service as scheduled. However, there are instances when due to unavoidable circumstances, restoration may extend beyond the published schedule.
    For more information, please contact our CALL CENTER at telephone no. 16211 / 631-1111, fax no. 1622-8554 / 632-8554, or e-mail address callcenter.tech.assist@meralco.com.ph. For faster resolution of inquiries, please use the Bill ID Number or Service Identification Number (SIN) indicated in your electric bills.
    For those who prefer to receive this schedule via e-mail, simply write to us at callcenter.tech.assist@meralco.com.ph and type in the phrase "Request for weekly schedule".



    VIEW YOUR BILL ON LINE. VISIT OUR WEBSITE!
    www.meralco.com.ph



    *Additional PPI

    Privileged/Confidential information contained in this e-mail and its attachment/s is intended solely for the use of the addressee and is not meant for reproduction, disclosure and distribution to others without previous authorization from Meralco or its authorized representative.  If erroneously sent or received, please do not open and delete the same from your system.  Unless, otherwise specifically stated and confirmed by the authorized representative of Meralco, the opinions and views that may be contained therein are personal to the sender.