MERALCO Maintenance Schedule for July 14 - 20, 2014 (Grp2) (Sent by: Janice V. De Asis)

=======================================================================
WELCOME TO MERALCO'S MAINTENANCE SCHEDULE VIA E-MAIL
------------------------------------------------------------------------------------------------------------------

Attached is the schedule of our pre-arranged power interruptions for July 14 to 20, 2014.  This serves as a general information guide and should not be directly construed as an interruption advisory to the e-mail recipients.

Please call us at telephone numbers 16211 or 631-1111 for verification of power interruption schedule.

If you wish to unsubscribe, please send us an e-mail and type in the word "Unsubscribe".

Thank you very much.



MAINTENANCE SCHEDULE

To carry out necessary maintenance and upgrading works on various MERALCO distribution facilities, electric service will be temporarily interrupted on the following dates and places:


TUESDAY, JULY 15, 2014
CAVITE (ALFONSO; AND TAGAYTAY CITY)
    BETWEEN 9:00AM AND 2:00PM – PORTION OF CIRCUIT TAGAYTAY WEST 312TGW
    Portion of Tagaytay – Alfonso National Highway from Western Union Residence Inn to Alfonso – Nasugbu Municipal boundary including Tagaytay Country Homes II Subd.; Bgys. Neogan, Mendez Crossing East, Bagong Tubig, Asisan and Zambal in Tagaytay City; Royal Tagaytay Estates Subd., Buck Estate, La Prairie Subd., Garden Hills Subd., Valley Farm Subd. and Scottsdale Classic Country Homes Subd.; Bgys. Amuyong, Bilog, Buck Estate, Kaysuyo, Kaytitinga I – III, Luksuhin Ibaba, Luksuhin Ilaya, Palumlum, Sikat, Sinaliw Munti and Upli in Alfonso.

    REASON:   Replacement of rotten crossarms and various maintenance works along Tagaytay – Alfonso National Highway in Bgy.  Neogan, Tagaytay City, Cavite.

TUESDAY TO WEDNESDAY, JULY 15 – 16, 2014
MAKATI CITY
    BETWEEN 11:30PM AND 11:59PM (TUE., 07/15/14) AND THEN BETWEEN 4:00AM AND 4:30AM (WED., 07/16/14) – PORTION OF CIRCUIT URDANETA 43VS  
         Hotel Céleste, AIM Conference Center and New World Hotel along Antonio Arnaiz Ave. (Pasay Road) in Bgy. San Lorenzo.
         Portion of Ayala Ave. from Bankers Centre Bldg. to and including Allied Bank Bldg., National Life Insurance Bldg., SGV I Bldg., SGV II Bldg., Bankmer Bldg. and one feed of PLDT Main Bldg. in Legaspi Village.  

    BETWEEN 11:30PM (TUE., 07/15/14) AND 4:30AM (WED., 07/16/14) – PORTION OF CIRCUIT URDANETA 43VS  
         Portion of Paseo de Roxas from Antonio Arnaiz Ave. (Pasay Road) to Dela Rosa St. including Legaspi St.; Asian Institute of Management, Greenbelt Mall Arcade, The Greenbelt Mall and Greenbelt – 5 in Legaspi Village, Bgy. San Lorenzo.

    REASON:    Commissioning of new 34.5kV electric circuit Legaspi 432RA in Legaspi Village, Makati City.

FRIDAY TO SATURDAY, JULY 18 - 19, 2014
**CAVITE (BACOOR)
    BETWEEN 11:00PM (FRI., 07/18/14) AND 4:00AM (SAT., 07/19/14) – PORTION OF CIRCUITS IMUS 422WK AND 423WK
    Portion of Molino Road from near Avenida Rizal ST. to and including Camella Springville West Phases 1, 2, 3, Camella Springville Central Phases 1, 2, 3 & 4, Camella Springville East Phases 1 & 2, Camella Springville South Phase 1, Camella Cerritos, Macaria Homes Phase 1 and Ponticelli Subd.; Perpetual Help College of Rizal and Supermart in Bgy. Molino II and III.
    Portion of Daang Hari Road from Sea Oil Gas Station to and including Cuevasville Subd., Camella Springville South Phase 2, Camella Springville Executive Subd. Phases II, Camella Springville Meadows, Lessandra Executive Village and Cerritos Heights in Bgys. Molino III and IV.

    REASON: Relocation of facilities affected by DPWH road widening project along Molino Road in front of Camella Springville Subd. in Bgy. Molino III, Bacoor, Cavite.

SUNDAY, JULY 20, 2014
CAVITE (GMA); AND LAGUNA (SAN PEDRO)
    BETWEEN 12:01AM AND 5:00AM – PORTION OF CIRCUITS GMA 41XF, 43XF AND 45XF
    Portion of Congressional Road from Altierra Subd. to near Mormon Church including Casa De Monteverde Subd. in Bgys. Francisco Reyes, Tiniente Tiago and Gregoria De Jesus, GMA, Cavite.
    Portion of Ramon Magsaysay Ave. from St. Joseph Ridgeview Subd. to near Reyvil Compound including St. Joseph Village 9 & 10, Villa Rosa Subd., Colina Subd., Filinvest Southern Heights II Subd., Villa San Pedro and Villa Consolacion in Bgys. Langgam, Estrella, Bagong Silang and Magsaysay, San Pedro, Laguna.

    REASON:     Replacement of rotten cross-arms and insulators along Congressional Road in Bgy. Gregoria De Jesus, GMA, Cavite.

BATANGAS PROVINCE (BATANGAS CITY; AND SAN PASCUAL)
    BETWEEN 1:00AM AND 5:00PM – THE WHOLE OF CIRCUITS NGCP - BATANGAS – BOLBOC 58BS; NGCP - BOLBOC 33ZZ AND 32ZZ; AND MAHABANG PARANG 32WZ
    Cocochem Agro-Industrial Park in Bgy. San Pascual, San Pascual.
    Bgys. Soro-soro Karsada, Bukal, Concepcion and Mahabang Parang in Batangas City.

    REASON:     NGCP Job:
      1. Replacement of rotten pole & cross-arms along Batangas City National Road in Batangas City.
       Meralco Job:
        2. To provide safe clearance during the erection of self support steel pole and conductor stringing along Diversion Road and National Road, Batangas City.
        3. Maintenance works inside NGCP Bolboc substation.

MANILA (ERMITA, MALATE AND PACO)
    BETWEEN 7:30AM AND 7:45AM AND THEN BETWEEN 1:15PM AND 1:30PM – PORTION OF CIRCUIT TEGEN 45B
    Portion of Zobel St. from Romualdez St. to San Marcelino including Teresa St. in Ermita.
    BETWEEN 7:30AM AND 8:00AM AND THEN BETWEEN 1:00PM AND 1:30PM – PORTION OF CIRCUIT TEGEN 45B
    Portion of Gen. Luna St. from near Padre Faura St. to Escoda St. including Swiss Inn and The Garden Plaza Bldg. 1 & 2, in Paco.
    Portion of F. T. Benitez St. from Escoda St. to near J. Nakpil St. including San Marcelino, Gen. Malvar and Modesto Sts.; DY International Bdlg. and New Gold Bond Marketing in Ermita and Malate.

    BETWEEN 7:30AM AND 1:30PM – PORTION OF CIRCUITS TEGEN 45B; AND TEGEN 46B – ERMITA 43S
    Portion of United Nations Ave. from Romualdez St. to near Taft Ave. including Tabacalera Cigars Bldg., Balite Flood Gate, Puregold Head Office, Philtrus Bank Insurance Commission of the Philippines, Lacson Commercial, Loadstar Shipping Company, Manila Teacher's Savings and Loan Association (MTSLAI), Philippine Bible Society, Simon Enterprises, Philippine President Lines, Philippine President Lines, Emilio Aguinaldo College, YIC Bdlg. and Western Police District in Ermita and Paco.
    Portion of San Marcelino St. from Zobel St. to Padre Faura St. including The Area President of the Church of Jesus Christ of Latter Day Saints, Jinss Lee Printing, Emilio Aguinaldo High School, Adamson University – Cardinal Santos Bldg. and Technological University of the Philippines (TUP) in Ermita.

    REASON:    Replacement of rotten poles along U.N. Avenue in Ermita and Paco, Manila.
QUEZON PROVINCE (LUCENA CITY; PAGBILAO; AND TAYABAS)
    BETWEEN 9:00AM AND 5:00PM – THE WHOLE OF CIRCUITS TAYABAS 44ZY AND 51ZY; AND PORTION OF CIRCUIT TAYABAS 48ZY
    Portion of Lucban – Tayabas National Road and Quezon Ave. from Lucban – Tayabas municipal boundary in Bgy. Dapdap, Tayabas to L. F. Teachers Village in Bgy. Cotta, Lucena City including Sitio Don Elpidio, Dela Torre Subd.,  Roma Rosa Subd., Doña Carmen Subd., Green Valley Subd., Sitio Isla Verde, Sitio Luad Loob, Tuazon Subd., St. Jude Village, Lita Subd. Phases 1 & 2, Angeles Zone Subd. I, II & III, Carmenville Subd., Lovely Meadows Subd., Lovely Village, Sumilang Subd. and Laval Subd. in Bgys. Camaysa, Dapdap, Ibas, Lalo, Matuena, Opias, Lita, Tongko, Wakas, Pandakaki, Mayowe, town proper in Tayabas, Quezon; Andaman Village, Capistrano Subd., De Mesa Cpd., Hermana Capistrano Subd. I & II, Pilar Cpd., Rey-Mar Cpd., Ridgewood Park Subd., San Isidro Subd., St. Micheal Subd., St. Peter Subd. II, Lopez Subd., Capitol Homes Subd., San Fernando Cpd., Zoleta Cpd., A. Orgas Subd., Campo Subd., Employees Village, Josephine Subd., L.I.C. Cpd., Marilag Village, North Employees Village, Pag-ibig Park Subd., Regis Cpd., Zaballero Subd., Marktown Subd., La Milagrosa Subd., Mt. Carmel Subd. and Sabina Subd. in Bgy. Cotta, Gulang – Gulang, babang Dupay, Ilayam and city proper in Lucena City.
    Along Padre Gomez St. and Pagbilao – Lucena Road from Quezon Ave. in Lucena city proper, Lucena, Quezon to and including the whole of Pagbilao; San Rafael Ville Subd., Santa Teresa Subd., Alpsville Subd., Cleade Heights Subd., Family Land Subd., Lucena Green Meadows Subd., R.J. Ville Subd., Riverside Subd., San Francisco Village, Villa Consuelo Subd., Villa Juliana Subd., Villa San Lorenzo Subd., VSJ East Subd., Bestland Homes Subd., Bliss Subd., Hills View Solcom Ville, Calmar Homes Subd., Executive Ville, Maryville Homes Subd., St. Thomas Village and Marville Subd. in Bgys. Barra, Dalahican, Ibabang Dupay, Mayao Castillo, Mayao Crossing, Mayao Kanluran, Mayao Parada, Mayao Silangan, Talao – Talao and city proper in Lucena City.
    Portion of Lucena Diversion Road from Palm Springs Subd. to Pagbilao - Lucena Road including Good Luck Subd., Happy Family Subd., Villa Aurea Subd., University Village, Grand Alliance Subd. and Metropolis Lucena Subd. in Bgys. Bocohan, Domoit, Ibabang Dupay, Ilayang Dupay, Mayao Kanluran & Silangan, Gulang – Gulang and city proper in Lucena City.

    REASON:   1.   Relocation of facilities along Tayabas – Lucban National Road affected by DPWH road widening project in Bgy. Camaysa, Tayabas, Quezon.
               2.   Relocation of facilities along Maharlika Highway affected by DPWH road widening project in Bgy. Ibabang Dupay, Lucena City, Quezon.
      3.   Preventive maintenance and testing works inside Meralco - Tayabas substation.
    MERALCO exerts all efforts to restore electric service as scheduled. However, there are instances when due to unavoidable circumstances, restoration may extend beyond the published schedule.
    For more information, please contact our CALL CENTER at telephone no. 16211 / 631-1111, fax no. 1622-8554 / 632-8554, or e-mail address callcenter.tech.assist@meralco.com.ph. For faster resolution of inquiries, please use the Bill ID Number or Service Identification Number (SIN) indicated in your electric bills.
    For those who prefer to receive this schedule via e-mail, simply write to us at callcenter.tech.assist@meralco.com.ph and type in the phrase "Request for weekly schedule".



    VIEW YOUR BILL ON LINE. VISIT OUR WEBSITE!
    www.meralco.com.ph



    **Revised PPI (changes already incorporated)

    Privileged/Confidential information contained in this e-mail and its attachment/s is intended solely for the use of the addressee and is not meant for reproduction, disclosure and distribution to others without previous authorization from Meralco or its authorized representative.  If erroneously sent or received, please do not open and delete the same from your system.  Unless, otherwise specifically stated and confirmed by the authorized representative of Meralco, the opinions and views that may be contained therein are personal to the sender.